Supreme Court Upholds "No Interest" Clause in Government Contracts | M S Sulthan
Disclaimer: As per the rules of the Bar Council of India, this content is for educational and informational purposes only. It does not constitute legal advice.

Supreme Court Upholds "No Interest" Clause in Government Contracts: Kerala Water Authority v. T.I. Raju

By M S Sulthan Legal Associates, Kozhikode | March 5, 2026 | Civil & Property / Dispute Resolution

The Supreme Court of India recently delivered a decisive and highly anticipated judgment concerning a government contractor's right to claim interest on delayed payments. For infrastructure companies and civil contractors operating under tight margins, delayed payments by state entities are a notorious hurdle. However, this recent ruling sends a stark warning: if your contract explicitly bars interest on late payments, the courts will firmly hold you to that agreement.

Background of the Dispute

The litigation originated from a preliminary agreement executed on April 30, 2013. T.I. Raju, a government contractor, was awarded the tender to construct a Sewage Treatment Plant at the Medical College in Calicut for the Kerala Water Authority (KWA).

The construction work was successfully completed and handed over on July 7, 2014, leaving a pending principal sum of Rs. 86,64,846. After the contractor filed a Writ Petition in 2015 to expedite the release of funds, the High Court intervened, and the KWA subsequently disbursed the principal amount in full by March 2, 2016.

However, the dispute did not end there. Following the receipt of the principal amount, the contractor filed a civil suit on November 25, 2017, demanding interest at a steep rate of 14% per annum for the delay between the work's completion (July 2014) and the final disbursal (March 2016).

  • Trial Court Verdict: The trial court initially favored the contractor, decreeing that the Kerala Water Authority was liable to pay Rs. 21,48,411 calculated at an interest rate of 14%.
  • High Court Modification: On appeal, the High Court upheld the contractor's right to interest but modified the decree by reducing the interest rate to 9% per annum, bringing the payable sum down to Rs. 12,90,469.

The Core Legal Issue: Clause 5

The crux of the matter before the Supreme Court was whether the contractor could legally sustain a claim for interest despite a specific, prohibitory clause embedded in the original preliminary agreement.

The Restrictive Clause: Clause (5) of the agreement explicitly stated that the settlement of claims would depend strictly on the availability of budget provisions and fund allotments from the government. Crucially, the clause mandated: "No claims or interest for damages whatsoever shall be made for the belated settlement of claims of bill".

The Supreme Court's Reasoning

Overturning the High Court's decision, the Supreme Court sided with the Kerala Water Authority, delivering a masterclass on the sanctity of commercial contracts and statutory interpretation.

1. The Binding Nature of Contracts

The Court emphasized the doctrine of *Pacta Sunt Servanda* (agreements must be kept). The contractor had voluntarily reviewed, accepted, and signed an agreement containing Clause 5. By doing so, he entered the commercial transaction fully aware that payments could be delayed due to bureaucratic funding issues, and he explicitly agreed not to claim consequential interest as damages for those delays.

2. The Power of The Interest Act, 1978

Section 3(3) of the Interest Act, 1978: The Supreme Court noted a critical oversight by the High Court. Section 3(3) explicitly permits parties to contractually agree to forgo accrued interest on delayed payments. The law allows competent parties to "contract out" of their right to claim interest, making Clause 5 perfectly valid and enforceable.

3. Overriding Effects (Section 34 CPC)

The contractor’s legal team attempted to rely on Section 34 of the Code of Civil Procedure, 1908 (CPC), which grants courts the discretionary power to award interest on decreed sums. However, the Supreme Court clarified a vital legal distinction: Section 34 merely addresses the rate and grant of interest by a court during litigation; it does not override or invalidate the substantive exceptions specifically outlined in Section 3(3) of the Interest Act, 1978.

4. Public Interest Priority

Lastly, the Court took judicial notice of the nature of the contracting party. The Kerala Water Authority falls under the definition of 'State' per Article 12 of the Constitution of India. The primary goal of the agreement was to initiate a vital public infrastructure project (a Sewage Treatment Plant for a Medical College) so citizens would not suffer. The Court recognized that funding availability is a known, systemic hurdle for State entities, which justified the inclusion of Clause 5 to protect the public exchequer from ruinous penalty claims.

The Final Verdict & Corporate Takeaway

Finding that it could not support the High Court's legal reasoning, the Supreme Court set aside the impugned orders. The appeal filed by the Kerala Water Authority was allowed, while the cross-appeal filed by the contractor, T.I. Raju, was dismissed.

The Corporate Takeaway: For civil contractors and vendors dealing with government bodies, this judgment serves as a critical warning. You can no longer rely on civil courts to "rescue" you from harsh contract terms you voluntarily signed. When bidding for government tenders containing "No Interest on Delay" clauses, contractors must factor the cost of potential payment delays directly into their initial project estimations and margins, as that interest will not be legally recoverable later.

Frequently Asked Questions (FAQ)

1. Can a contractor claim interest if the contract explicitly forbids it?
No. As affirmed by this Supreme Court judgment, if an agreement contains a clear, unambiguous clause barring the claim of interest on delayed payments, the courts will enforce that clause under Section 3(3) of the Interest Act, 1978.
2. Doesn't Section 34 of the CPC give the court power to award interest anyway?
Section 34 of the Civil Procedure Code gives the court discretion to award interest from the date of the suit to the date of the decree. However, the Supreme Court clarified that this procedural discretion cannot override a substantive statutory provision like the Interest Act, which explicitly allows parties to contractually waive their right to interest.
3. Does this ruling apply to private contracts between two companies?
Yes, the principle of contracting out of interest under Section 3(3) of the Interest Act applies to private commercial contracts as well. However, in private contracts involving Micro, Small, and Medium Enterprises (MSMEs), the MSMED Act, 2006 often overrides such clauses, statutorily mandating compound interest for delayed payments regardless of the contract terms.
4. Why did the court highlight the "Public Interest" aspect?
The Court noted that the Kerala Water Authority is a State entity operating for the public good. State projects often face delays in budget allotments. The "no interest" clause was a known condition designed to protect public funds from escalating delay penalties, a risk the contractor knowingly accepted to secure the public tender.

Engaging in high-value infrastructure or government contracts? Contact our Civil & Property Dispute Resolution desk to review your tender agreements before signing.

βœ‰οΈ contact@mssulthan.com

Β© 2026 M S Sulthan Legal Associates, Kozhikode. All Rights Reserved.

Loading latest insights...

Newsletter

Don't miss our future updates! Get subscribed today!

MS Sulthan

Legal Associates

MENU

CONTACT

+919847980019

+91-4953552516

contact@mssulthan.com

T1, Ground Floor, Hi-Lite Business Park, Kozhikode, Kerala - 673014

136/2, Rameshwar Nagar, Model Town, New Delhi – 110033

Β© 2026 MS Sulthan Legal Associates. All rights reserved.